Tower Building exercise
In
the Tower Building exercise there are many learning on personal as well as
professional level. These exercises are also used extensively in the corporate for Team Building exercises.
I
have learned few lessons from these exercised performed in the class.
Fostering
Communication:
The communication
between the participants is very important for success of any organisation. The
person who was placing the blocks needs to communicate in perfect way with the supporting
person so that the coordination is maintained. Communication is the key for
performing the activities in tandem with other person. Leaving any gap in this
process can cause the efforts to go in the conflicting directions and cause the
tower to fall.
Experience:
While working in the
project, the communication between the project site and the coordination office
is very important for the completion of the project. The slight
miscommunication in the specifications of the materials can cause havoc in the
project. Even while using the electrical equipment, the person working on the
maintenance for the equipment’s needs to be in perfect understanding with the
operation people. In case the equipment’s are left live and the maintenance
person starts working on them, it can cause a fatal accident and damage to the
property.
Setting a Goal: While working on the exercise the even the single
person or in case of the group, a vision was needed to form. The goal was a
tool for focusing on the activity and giving the 100% efforts to achieve it.
The goal in very much needed in the corporates to have a common target to
achieve. The clarity in this respect gives momentum to the staff and the
management to achieve them. A goal is like a Lamp, in story of Birbal, where a
person stands in the cold water of the river with only a lamp insight. The goal
gives a motive for the organisation to fight the challenges coming in the way
to achieve the target.
Experience: I was a part of a Solar Project of 25MW, in my
company. This was the biggest project in solar at the time of its conception.
Our company had goal for the project, to complete it in the record time. The
team for the project was given a task to complete this project within Seven
Months. To meet reputation of the Department, team decided to complete it
within Six Months. After deciding the goal, every person went extra mile to
achieve the seemingly impossible task.
The Tower Building was a reminder of the same.
Deciding responsibilities:
In the exercise the
roles of the persons were decided and a proper authority is given. The person
building the tower should not be disturbed so that the tower does not fall. On
the contrary they can give suggestion to him to make a better and taller tower.
This shows the clear division between the implementer and the planning and
managing wings of the organisation. Everybody is expert in owns field. He knows
the trades of the business and can take decisions on the tacit knowledge gained
with experience. Detractors can also say that, a person from different
background can provide a better and different solution to the problems. So,
there needs a limit, boundaries between the authority of people to make the
process move smoothly and flexibility is also possible.
Experience: In the
project activities, the critical and important decisions are always taken by
the Project Head and he is assisted by others to support the decision based on
the specific requirements. While implementing the decision, people can take
their decision on the last stages of implementation. This gives certain
flexibility at the time of execution and changes can take place on requirement
of the site conditions.
No comments: